Hi Naga,
This SAP note nails the problem. Thanks for sharing it.
Lead time for the parent item = 105. The number holidays up to product delivery date = 4.
27/03/2015 - 105 - 4 = 08/12/2014, which is the due date in the stock status.
Thanks & Regards
K