Hello Carlos,
Planned/production order basic dates are always calculated according to the plant factory calendar.
Production order will do scheduling base on work center's factory calendar,not base on plant calendar.
Please refer consulting note 46237 - Consulting: determination of the order dates
Best Regards,
R.Brahmankar